Council reviews public works building RFP plans, raises budget and scope questions

3810970 · June 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council members discussed correcting an inaccurate RFP advertisement, a phased bidding approach for plumbing/electrical work, internal construction tasks the city will perform, and outstanding cost estimates for completing the public works building.

Price City Council members discussed the procurement approach and budget for a new public works building and directed staff to proceed with targeted bidding for mechanical and electrical work.

Staff said an incorrect advertisement for the project was circulated by mistake last week; the correct scope for the immediate procurement is plumbing, HVAC and electrical work. The council heard that the foundation and most exterior work are complete, and that the city intends to bid interior mechanical trades by schedule line items so it can award parts of the work if the full package exceeds available funds.

Council members repeatedly asked staff to identify the total cost and to confirm which portions of the project the city can complete in-house. Staff said the streets department will do interior framing, exterior paving and some site work; they estimated the in-house dirt and site prep work has saved roughly $75,000, and that the parking-lot and related site work could cost a contractor about $150,000 if contracted out (figures given in the meeting were presented as estimates). Staff emphasized electrical work must be done before the shop can operate and that available in-house electricians are already heavily scheduled.

No formal vote was recorded; staff said they would advertise the corrected bid package for mechanical and electrical work next week and would use schedule-based bids that allow partial awards based on budget availability.