District says HVAC retrofit design complete but permits, utility timeline could delay work
Summary
Emmett Independent District staff told trustees the EMS HVAC retrofit is fully designed and long-lead equipment is ordered, but state permit review and Idaho Power’s service timeline are unresolved and could affect budget and schedule.
Emmett Independent District staff updated the board on the EMS heating, ventilation and air-conditioning (HVAC) project, saying design work is complete but the district still needs state and city permit approvals and a utility service agreement before major on-site work begins.
The update, delivered by district staff member Mister Kimball, said the district has submitted permit applications to the city and the state and is seeking a waiver of certain review fees for public schools. Kimball said the state reviews plumbing, mechanical and electrical plans and that comments from that review could require small changes to the design. He added long-lead HVAC equipment has been ordered and will be…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat