Beaumont council approves $3.31 million contract for citywide street improvements

5448054 · July 17, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Beaumont City Council voted to award the construction contract for the fiscal-year annual citywide improvements project, CIP R25-01, to Vance Corporation and authorized alternates and a 10% contingency for a total construction cost of $3,309,711.

The Beaumont City Council voted to award the construction contract for the fiscal-year annual citywide improvements project, CIP R25-01, to Vance Corporation and authorized alternates and a 10% contingency for a total construction cost of $3,309,711.

City staff Robert Vestal presented the project and procurement results, saying, “Their base bid was 2,877,000.” Vestal told the council the city published the request for bids on May 7 and received five bids on June 12, with Vance Corporation the low bidder. Vestal said the recommended total includes several alternate bids (including paving the alley behind Napa) and a 10% contingency.

Council discussion focused on construction management and inspection. Council member Fenn asked about a staff note that the city intends to use NV5 to provide supplemental construction management and inspection from an on-call contract and observed there was roughly a $700,000 difference between the low bid and the next bidder. Vestal said NV5 would assist the city inspectors and have a city representative at the asphalt plant to verify materials, and that the city’s preliminary estimate for NV5 services is about $100,000. He also said NV5 has supplemented the city’s inspection efforts on prior street projects.

There were no public comments on the item. A council member moved to approve the recommended action; another council member seconded. On a roll call, Council member Fenn, Council member Martinez, Mayor Pro Tembois and Mayor Lara voted yes; Council member White was recorded as excused/absent. The motion carried and the council adjourned shortly afterward.

The vote and contract award advance the city’s CIP R25-01 citywide improvements; staff indicated NV5 will provide supplemental inspection services during construction and that specific plant-level verification will be done once the contractor notifies the city which asphalt plant will be used. The motion approved the award to Vance Corporation and the established contingency; staff did not provide a final executed contract amount at the meeting.

The council did not identify funding sources or a construction start date during the discussion. Staff said final inspection costs were still being obtained and provided only a preliminary estimate for the supplemental inspection services.