Summary

Finance and Public Safety committees recommended adding a five‑year Axon body‑worn camera program, including an AI transcription feature, to the county budget. Committees flagged an estimated $1.4–1.5 million total cost and said officials have not provided concrete projected savings.

Manitowoc County Finance and Public Safety committees unanimously recommended adding a five‑year Axon body‑worn camera program — including an AI transcription component — to the county’s budget, county supervisors said at the July meeting.

Committee members said the program would span five years with total implementation costs discussed at roughly $1.4 million to $1.5 million; committee discussion included an average annual cost estimate of about $289,000. The AI component of the proposal was described as an additional upfront cost the vendor discounted from about $250,000 to roughly $200,000 for the first year.

The recommendation came after a joint Finance/Public Safety meeting where the sheriff’s office presented an Axon contract proposal and described operational challenges. Supervisor Michael Hanson, who reported the committee discussion to the county board, said the AI element would “watch the video, listen to the recordings … put everything in a document so that the officer then can edit it,” allowing officers to shorten time spent on report writing.

Hanson also noted the committee did not receive a concrete estimate of how much money the county would save if officers spent less time on paperwork. “There was no concrete amount of money that we would save that was given to us,” he said, adding that potential savings from reduced overtime or quicker report turnaround were not quantified in the presentation.

Sheriff Hartwick briefed committee members on department operations while the proposal was discussed; committee notes say the sheriff flagged physical and logistical challenges in implementing the Axon system. Public Safety committee reporting also mentioned staffing pressures, anticipated overtime overages and other operational factors that influenced deliberations.

Committee members voted unanimously to forward the proposal to the full county board and to include the program in the proposed budget for board consideration. No county board final adoption vote on the Axon contract was recorded in the transcript; committee leaders asked supervisors to review proposal materials and direct questions to the sheriff’s office or county executive before the board takes a final vote.

Next procedural steps noted in committee reports include follow‑up briefings and opportunities for supervisors to request additional information; the Public Safety committee’s next meeting was scheduled for August 13.