New Loretta Zumbro Elementary nears completion; permanent traffic signal delayed, temporary signal planned

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Core Construction reported the Loretta Zumbro Elementary project is approximately 95% complete; permanent power and life-safety inspections passed and furniture deliveries are under way. A permanent traffic signal is expected in fall; a temporary traffic signal will be installed July 25.

The board received a construction update from CORE Construction and the district on June 14 for the new Loretta Zumbro Elementary School campus. Whitney Bunn, CORE project director, said the project is about 95% complete, with the site reportedly approaching $25 million in cost-complete-to-date numbers provided in the update. Bunn told the board most concrete work was finished and the playground on the northwest corner of the site is complete; the site has permanent power from Arizona Public Service and life-safety inspections (including final fire inspections with the state fire marshal) were passed the morning of the update.

Bunn said roofing, HVAC units, interior finishes and landscaping…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans