Council approves amendment for 1600 North/400 East phase‑1 safety work; $460,000 project on consent

5374376 · July 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Orem City Council approved a consent resolution authorizing the mayor to sign an amendment to the interlocal agreement with Utah County to build phase 1 safety improvements at 1600 North and 400 East. The phase is estimated at about $460,000; a future roundabout remains a potential phase 2 pending funding.

Orem City Council voted on the consent agenda to authorize the mayor to sign an amendment to a 2022 interlocal agreement with Utah County to build phase 1 safety improvements at the intersection of 1600 North and 400 East.

City staff described the work as a roughly $460,000 phase to improve trail crossings and pedestrian safety while the city seeks funding for a larger roundabout project planned as phase 2. The amendment adjusts the original interlocal arrangement, which in 2022 contemplated about $1.3 million in MAG‑administered funds for safety improvements at the location.

"This is about a $460,000 project. Originally, in 2022, we signed an interlocal agreement with Utah County, which administers the MAG money to do safety improvements there for about 1,300,000.0," said Ryan, a city staff member, during the presentation. Staff said the work will ‘‘create more of a directional crosswalk system for those that use the trail’’ and include boulders and other features to channel pedestrians and cyclists toward marked crossings and away from diagonal crossings.

The presentation stated the city will pay roughly 6.77 percent of the phase‑1 costs as a local match and that a contractor is already on board. Staff did not provide a firm start date; one staffer said the two staff members who have the schedule were unavailable that evening.

The council approved the consent items, including the interlocal amendment, without separate roll‑call discussion. The amendment was described in the meeting packet as a reasonable change to reflect the phase‑1 scope and costs.

Planning documents and earlier outreach indicated public preference for a roundabout at the intersection; staff said that remains the preferred long‑term solution but will require additional funding and would be considered as phase 2.

Staff asked council members to direct any additional questions or constituent concerns to city staff; the amendment will allow the phase‑1 improvements to proceed while the city seeks funds for the larger project.

Votes at a glance: the interlocal amendment for the 1600 North/400 East project was approved on the consent agenda; individual vote names were not recorded in the public verbal roll call during the meeting.