Pines grade-separation piles nearly complete; girders due by month'end as bids reviewed
Summary
City reported progress on the Pines grade-separation project: secondary-track piles are complete, mainline piles are being driven and girders are expected by month'end; staff are reviewing bids and hope to award and break ground in August.
City management updated the council on the Pines grade-separation project, saying BNSF has nearly finished driving piles for the mainline bridge supports and that long-lead girders are expected by the end of the month.
City Manager John Hellman said the secondary-track piles were previously installed; the current work is for mainline piles and requires track windows when trains…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat