County engineer reports progress, delays on Justice Center and ARPA-funded projects

5322256 · July 7, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County Engineer John Hernandez told commissioners the Justice Center project is about 48% complete and ARPA-funded projects including fiber optics, generators, juvenile detention expansion and an animal shelter are at various stages; some items face delays tied to electrical and septic-system issues.

John Hernandez, county engineer, updated the court on construction and ARPA-funded capital projects.

Justice Center and schedule Hernandez said the most recent construction payout for the Justice Center was approximately $3.4 million and the project stood at about 48% complete. He identified second-floor electrical and plumbing work as critical-path items for the coming month and said commissioning should begin in March or April with project closeout planned for late spring or early summer.

ARPA-funded projects and status details - Fiber-optic project: Contractor FSG Telecom; about 58% complete. Hernandez said the project requires two railroad crossings and the county was finalizing Union Pacific Railroad permissions for underground boring. - Precinct 1 generator: Contractor Dawson Electric Company; about 90% complete with retainage remaining and final testing pending. - Civic Center generator: Contractor DC Energy; about 21% complete with the concrete pad in place. - Juvenile detention extension: Contractor Beck Brothers; roughly 40–43% complete. Progress was slowed by an electrical-panel tie-in issue the engineer said the project team is addressing. - Animal shelter: Contractor Beck Brothers; about 23% complete. Work slowed due to septic-system concerns involving human- and animal-waste design; the county and engineer are coordinating with TCEQ and engineers to finalize designs.

Hernandez emphasized coordination across engineering, grant teams and contractors, and noted retainage will be held until punch-list items are corrected. Commissioners asked about site appearance and irrigation damage; Hernandez said those items would be added to the punch list prior to final acceptance.

Why it matters: These projects represent significant capital spending and service investments for the county, affecting public safety, emergency operations and animal services. Electrical and septic-system issues can delay completion and increase oversight needs.

Next steps: The county will continue to track critical-path items and document punch-list and retainage issues until contractors complete repairs and systems testing.