Clovis plans fuel‑farm refurbishment; state aviation funding cited, temporary fueling plans outlined
Summary
Airport staff reported a Notice to Proceed for a fuel‑farm refurbishment that will replace piping, pumps and tanks (14–16 month lead time on tanks) and said they plan temporary waivers and operational measures during a brief on‑site installation window.
Clovis airport staff told the Veil Aviation Board they have issued a Notice to Proceed for a fuel‑farm refurbishment that will replace piping, pumps and tanks; staff said the tanks have a 14–16 month lead time and construction could begin as early as October 2025.
Innovative Fuels is the on‑station contractor, staff said, and the airport is pursuing installation of a Scully overfill prevention system so a second jet‑A truck can be returned to service. "With that Scully system…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat