Board approves repairs at Ojeda Middle School; trustees press for districtwide facilities prioritization

5065600 · June 23, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees approved repairs at Ojeda Middle School after staff described restroom refurbishments, painting and miscellaneous cleanup; some trustees said they preferred waiting for the full facilities assessment to prioritize districtwide needs.

The Del Valle ISD Board of Trustees approved a facilities-repair package for Ojeda Middle School during the June special meeting; the motion passed with a recorded result of 4-2.

Facilities presenter Steven Gonzales described work similar to Daley: restroom refurbishment with machine stripping, tile and grout cleaning, grout sealant application; repainting roughly 150,000 square feet of building space with drywall repairs and two coats of paint; removal or restoration of damaged tack/marker boards; cleaning of ductwork and gym exterior doors; and misc. classroom and hallway repairs. Gonzales said staff would like to start work the same week if the board approved and estimated a five-week timeline.

A trustee asked the presenter to identify safety concerns; Gonzales said some safety-related items include clocks on walls and security badge access systems but said the presentation focused primarily on cosmetic and cleanliness improvements. Several trustees said they toured the campus and that photos did not fully capture the condition.

Trustees discussed whether to delay action until the district's facilities assessment was reviewed; some members said they were reluctant to approve single-campus work without seeing the districtwide assessment. Others said equity and the need to set new principals up for success justified the targeted repairs. Secretary Guadion moved approval and Trustee Cisneros seconded; the motion passed 4-2.

The presentation did not list specific contract awards, vendor names, or a budget breakdown for the Ojeda work. Trustees again requested the district convene a prioritization process after the incoming chief operations officer reviews the facilities assessment.