Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Water Infrastructure topic

No spam. Unsubscribe anytime.

County approves expanded Spring Valley test well after crews find larger aquifer

4066880 · June 19, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The county approved a $133,400 change order to extend drilling of a Spring Valley test well to about 560 feet after crews discovered a deeper aquifer producing higher flow. The extended drilling is funded by an existing grant; staff will solicit bids for retrofit/pump installation next.

The Board of Supervisors approved change order number 1 to the construction contract for Spring Valley test wells on June 17 after well drillers discovered water-bearing formations below the originally planned test depth.

Special Districts Administrator Robin Foray told the board the original contract called for drilling to 300 feet at a cost of $147,000, but during drilling crews encountered rock layers and a deeper aquifer. The driller extended drilling to approximately 560 feet and completed reaming, casing and screening work. The change order for the additional work totals $133,400, bringing the contract value to $280,400.

Foray said preliminary pumping and testing show the deeper well may yield about 300 gallons per minute, a sizable increase compared with the county's existing water plant production of about 190 gpm. "This is a huge win for Spring Valley," Foray said, noting the well work is fully grant-funded and that the county had a state mandate to secure a secondary water source for the Spring Valley community. The item approved today covers drilling and completion; the county will solicit competitive bids for retrofitting the well with a pump and surface facilities.

Board action: Motion to approve change order and authorize the Special Districts Administrator to sign the construction contract change was offered and approved.

Why it matters: Spring Valley has only one primary access and a single water source; county staff and residents have sought improved emergency access and water redundancy. A productive test well that exceeds existing plant output would provide a backup source and reduce vulnerability for the community.

Next steps: Contractor will finish test pumping and water-quality sampling, staff will evaluate pump sizing and call for bids for the retrofit and pump installation, and the county will coordinate design and permitting for a production well and connection to the water system.