Glens Falls nearing final electrical design; long equipment lead times could extend project timeline
Summary
Staff reported the electrical upgrade design is at 90% and under internal review; they warned long lead times for switchgear and transformers could push procurement and construction out several years.
Get email alerts on the Infrastructure Electrical Upgrade topic
No spam. Unsubscribe anytime.
At the June 16 Water and Sewer Workshop, staff reported that the electrical upgrade design has reached the 90% stage and is in internal review.
Bill (staff member) said the project team is resolving discipline-level comments and preparing documents that the bank will require for financing. He cautioned that extended industry lead times for major electrical equipment—switchgear and transformers—have increased from months to as long as two to three years, which could lengthen procurement and construction schedules.
Staff described a likely sequence: finalize the 100% design and secure state approvals, then bid and contract for construction; equipment procurement and construction together could stretch the project over multiple years. Staff estimated a realistic delivery and construction schedule could extend to about four years from design completion on a favorable timeline.
Board members discussed the trade-offs of timing and technological change but did not change scope or direct staff to alter plans. No formal action was taken beyond receiving the update.
Ending: Staff will complete the 100% design and report back on procurement timing and needed financing documentation.