Summary

Contractors reported a higher-than-expected guaranteed maximum price for phase 2 of the Coffee County Law Enforcement Center and identified value-engineering items; commissioners approved Pay Application No. 19 and smaller contracts related to the project while project teams work to bring total cost back toward the $30 million bond cap.

Contractors and county staff told the Coffee County Board of Commissioners on Monday that phase 2 of the county's Law Enforcement Center is tracking above the project budget and they are pursuing value-engineering options to reduce costs.

The county's construction manager, River City Construction, provided a final guaranteed maximum price that, together with architect fees, furniture/fixtures/equipment and other owner costs, left the overall project tracking about $164,000 over the target the county has been using. River City said teams were pursuing roughly $220,000 in value-engineering credits, including lower-rated door assemblies, lighting-control changes and other scope reductions.

Attorney and project representatives also said partial occupancy of administrative and kitchen areas proceeded after a fire marshal inspection, but a smoke-control panel on the ductwork remained under troubleshooting. River City said the vendor Siemens was working on the panel and that, once that item is resolved, the fire marshal would not need to return for the partial-occupancy signoff.

"We're trying to work down those costs through value engineering," River City Construction representative Joe Seymour said. "We have a lot of things we're still working through, but that's kind of where we're at."

Why it matters: County officials said voters approved a bond and the county has committed to holding the project to a $30 million cap. Commissioners and court officials said they will prioritize safety- and security-related items while discussing what nonessential features could be deferred or removed.

What the commissioners approved Monday: - Pay Application No. 19 from River City Construction for the Law Enforcement Center in the amount of $1,503,874.99 was approved. The payment was described in the meeting packet and presented by county staff; commissioners voted to approve the application and to fund it from the county's JL Construction Project Fund (Fund 111).

- A separate budgeted allowance was approved to install a six-zone lawn irrigation system at the new detention-center grounds. The board authorized the chairman to sign Shullers Incorporated's proposal dated May 32, 2025 (invoice line) for $11,222.39 with funds to come from courthouse general building maintenance.

Project status and next steps: County staff, the general contractor and architect (GGA) said they will continue value-engineering work and meet with judges and other stakeholders to prioritize courtroom and court-support elements. River City said it will roll unspent contingencies and allowances from Phase 1 into Phase 2 where allowable; the team estimated roughly $120,000 may carry forward but said that figure remained provisional.

Commissioners said the court side will need to identify priorities and that commissioners will make final scope decisions. River City and the architect will present updated options in coming weeks for the board's review.