Committee reviews three HVAC bids for sheriff's office; Johnson Controls presents feasibility study and budget pricing

3319605 · May 15, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Johnson Controls presented a feasibility study and budget pricing for a multi-part HVAC replacement at the sheriff's facility, recommending a chilled-water system, makeup-air cooling and controls updates; the committee asked staff to compare the three proposals and return with an apples-to-apples recommendation.

The committee spent an extended session on options to upgrade the sheriff's facility HVAC system, hearing a detailed presentation from Ben Malone of Johnson Controls and discussing two other vendor proposals. The committee did not award a contract but directed staff and the sheriff's office to compare the three bids and return with clarifying details and a recommendation.

Johnson Controls presentation and recommended scopes: Ben Malone described a feasibility assessment and budget pricing packages called Facility Improvement Measures (FIMs). He said the largest recommended scope (FIM 1) would remove three legacy condensing units, install a new chilled-water plant, provide new chilled-water coils for air handlers 1 and 2, demolish aging air-handler 3 and replace it with a smaller, more accessible unit, and add a chilled-water coil to the kitchen makeup-air unit to control humidity. Malone emphasized the approach was budget-level pricing only and that engineering and any required structural roof reinforcement would be part of a subsequent engineering/design phase.

"These are budgets, budgets, budgets," Malone said repeatedly, cautioning that the figures were preliminary and contained contingency.

The presentation also included two boiler options under FIM 2 (either replace one boiler with an upsized dual-fuel boiler to reach an estimated 2.5 million BTU capacity or replace both boilers with two new 2.5 million-BTU boilers) and two controls options under FIM 3 (a partial controls upgrade tied to the new chiller or a full controls replacement to modern BACnet communications).

Budget ranges and key technical issues: Malone gave budget orders of magnitude for the proposals and said the work would be turnkey if the committee chose to proceed. He listed a partial-chiller-plus-controls budget at about $998,100 and a full replacement option at about $1,279,800 (numbers presented as budget pricing). He also warned of industry-wide refrigerant issues that have made continued repair of aging DX (direct-expansion) systems increasingly problematic, and argued that a chilled-water approach concentrates refrigerant outdoors in a chiller rather than running refrigerant to indoor coils.

Vendor comparison and committee direction: committee members and staff noted differences in scope among the three vendors (Johnson Controls, Jamar, and KBK). Members asked staff to confirm whether high-voltage wiring and tax were included in each vendor's numbers, to confirm the structural engineering needs for rooftop chiller placement, and to clarify warranty and factory-startup procedures. Malone noted Johnson Controls could offer Sourcewell cooperative-pricing if the committee desired that procurement route.

Concerns and priorities raised: committee members repeatedly voiced a preference for doing the work "the right way" up front to avoid repeated repairs. They also asked for a clear delineation of essential work versus desirable upgrades, and discussed phasing work across fiscal years to reduce borrowing. Committee members and the sheriff favored FIM 1 (the chiller/makeup-air priority) as most urgent, with boiler and controls upgrades possibly staged depending on budget.

Next steps: staff and the sheriff's office will gather apples-to-apples comparisons of the three written proposals, remove tax where the county is tax-exempt for clearer price comparison, confirm what is included or excluded (electrical service upgrades, asbestos abatement if present, roof structural upgrades), and prepare a packet for the full county board. No contract award was made at the meeting.