MPO staff report progress on Walnut Street, Third Street and multiple state projects

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

MPO staff provided a project update covering Evansville projects (Walnut Street Phase 3, Third Street), county road acquisitions and designs, and several NDOT/STATE projects including US 41 pavement replacement and I-64 maintenance work.

MPO staff provided progress reports on local and state-managed transportation projects in the Evansville area.

City of Evansville projects: Walnut Street Phase 3 has final asphalt placed from US 41 to Garvin Street; staff said an early summer completion of construction activities is anticipated. A new Third Street reconstruction project with multimodal improvements has a preliminary engineering contract awarded to Versus Engineering.

Vanderburgh County: Oak Hill Road right-of-way activity includes acquisition of 45 parcels with two parcels in condemnation for the Lynch Road to Saint George segment. Winberg Road stage 2 plans were submitted; right-of-way engineering is complete and Centerpoint Gas is acquiring a utility easement. Environmental documents were submitted to NDOT for comment.

Wharton County and other county projects: Epworth Road Phase 1 environmental document was released for public comment; Phase 2 has a notice to proceed for preliminary engineering. Minor projects and programmatic agreements were submitted to NDOT where noted.

NDOT/highway contractor highlights: Staff summarized multiple state and federal projects, including work on SR 57/I-69 (contract R42753) with a pre-final inspection completed, pedestrian bridge and intersection improvements on US 41 (B42876), US 41 pavement replacement (R41410) with ongoing asphalt placement, and Lloyd Expressway/State Route 62 work on the west side of Evansville (R42287) where beams are being set and bridge demolition is ongoing. Staff also highlighted I-64 pavement maintenance (R43248) and US 41 HMA overlay design activity (R45274).

Staff invited questions; none were raised during the meeting.