Harris Street drainage phase complete; east‑side drainage easement under negotiation with Huggins Ranch

3276058 · May 12, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Contractor completed 36‑inch drainage pipe installation on Harris Street first phase and sanitary sewer installation; detention pond excavation to begin. On the city's east side drainage (Fourth Street) project, staff and Huggins Ranch continue negotiations over an easement; a revised easement was sent May 6 and is under review.

Public works staff reported progress on two city infrastructure projects at the May 12 Fulshear Development Corporation meeting.

For the Harris Street project, the contractor has completed installation of the 36‑inch drainage pipes for the first phase (the stretch from FM 1093 to Second Street), except…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans