The Norton Planning Commission unanimously approved SPR 6 20 25, a major site plan review allowing an almost 6,000‑square‑foot addition to an existing industrial building at 3668 Summit Road. City staff said the engineer's comments were addressed and a zoning permit will be issued without council review.
Get email alerts on the Site Plan Review topic
No spam. Unsubscribe anytime.
The Norton Planning Commission voted unanimously to approve SPR 6 20 25, a major site plan review for 3668 Summit Road that allows a roughly 6,000‑square‑foot addition to an existing industrial building.
City zoning staff told commissioners that the project’s engineer reviewed the submitted plans, the applicant addressed the engineer’s comments and the plans were recommended for approval. “All comments have been complied with and the plans are recommended for approval,” the zoning inspector said during the meeting.
The applicant team said the addition will be built on the south side of the existing commercial building. “It’s just under 6,000 square foot addition to the south side of it,” Matt Duncan of Davie Resource Group said, adding the new space will be primarily open and used for storage and related operations.
According to the site plan and statements at the meeting, the property is I‑1 zoned. The front portion of the building is occupied by an office and serves as the operations base for a trucking business; commissioners were told that portion employs about four people. The applicant and staff noted the plan shows a 1.5 parking‑space-per‑employee ratio, a handicapped space, and large gravel extents used for trailer storage. The back addition will not include plumbing and will be primarily open space with lighting, the applicant said.
Commission members asked a few operational questions about parking and plumbing; no concerns blocked the application. The zoning inspector confirmed the site plan met engineering and zoning comments and that the item does not need to go to city council. Staff said the applicant will receive the zoning permit via email once finalized.
Votes at a glance
- SPR 6 20 25 — Major site plan review for 3668 Summit Road: approved (roll call: Witzberger, Leyda, Dowling, Coughlin, Peterson — yes). Mover/second: not specified in transcript. Notes: city engineer’s comments addressed; no council review required; zoning permit to be issued by staff.
- Approval of Planning Commission meeting minutes, April 8, 2025: approved (roll call: majority yes; Mr. Compton abstained). Mover/second: not specified in transcript.
During the meeting staff previewed items expected on the commission’s May 28 agenda, including a conditional‑use permit application from TRX Properties for storage containers on Barber Road, a replat for Brookside Greens Clubhouse, and a preliminary site plan submitted by Norton Energy Storage for a project at the PPG site that will also require a development agreement with council and a variance before the Board of Zoning Appeals.
The commission adjourned after handling the listed items.