Board approves Wilder Elementary addition; approves parking‑lot alternate to ease drop‑off traffic
Summary
The board approved a guaranteed maximum price (GMP) for an addition and renovation at Wilder Elementary that will add classrooms and administrative space and remove a portable; the board also approved an alternate to add parking and a drop‑off lane to improve safety.
Get email alerts on the School Construction topic
No spam. Unsubscribe anytime.
The school board approved a guaranteed maximum price (GMP) for Wilder Elementary School’s addition and renovation project and accepted an alternate to add a parking lot and drop‑off lane to improve traffic and safety near the building.
At the May 12 meeting the finance committee and district architects described the project as a multi‑phase build that will add three classrooms in phase 1 — a new administrative suite and one classroom in the new addition and two renovated classrooms in the former office footprint — and later allow removal of two relocatable classrooms when phase 2 proceeds. The project’s total budget increased from earlier estimates because of additional allowances for FF&E (furniture, fixtures and equipment) and higher owner contingency amounts.
Nut graf: Trustees approved a GMP that funds the immediate addition and associated renovations; the board also approved a $150,672 parking‑lot alternate to add roughly 13 staff parking spaces, a handicap and visitor parking and a drop‑off lane to reduce street congestion during arrival and dismissal.
Construction engineers told trustees the total project cost moved from an earlier estimate of about $2.7 million to roughly $3.1 million because of uncovered soft‑cost allowances and the added parking alternate. The finance committee recommended approving a GMP of approximately $2.452 million and a total project budget near $2.954 million, plus the parking alternate at $150,672.
The board voted to approve the GMP and the parking alternate (motion moved by Palmasino; second by Dr. Lund). A roll call recorded all present members voting yes; Flynn was absent.
Ending: Administration said phase 1 work will be prioritized so the addition shell can be enclosed during the summer and interior work completed during the following school year; phase 2 remains designed for a later date pending funding and scheduling.