Board approves Wilder Elementary addition; approves parking‑lot alternate to ease drop‑off traffic

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved a guaranteed maximum price (GMP) for an addition and renovation at Wilder Elementary that will add classrooms and administrative space and remove a portable; the board also approved an alternate to add parking and a drop‑off lane to improve safety.

The school board approved a guaranteed maximum price (GMP) for Wilder Elementary School’s addition and renovation project and accepted an alternate to add a parking lot and drop‑off lane to improve traffic and safety near the building.

At the May 12 meeting the finance committee and district architects described the project as a multi‑phase build that will add three classrooms in phase 1 — a new administrative suite and one classroom in the new addition and two renovated classrooms in the former office footprint — and later allow removal of two relocatable classrooms when phase 2 proceeds. The project’s total budget increased from earlier estimates because of additional allowances for FF&E (furniture, fixtures and equipment) and higher owner contingency amounts.

Nut graf: Trustees approved a GMP that funds the immediate addition and associated renovations; the board also approved a $150,672 parking‑lot alternate to add roughly 13 staff parking spaces, a handicap and visitor parking and a drop‑off lane to reduce street congestion during arrival and dismissal.

Construction engineers told trustees the total project cost moved from an earlier estimate of about $2.7 million to roughly $3.1 million because of uncovered soft‑cost allowances and the added parking alternate. The finance committee recommended approving a GMP of approximately $2.452 million and a total project budget near $2.954 million, plus the parking alternate at $150,672.

The board voted to approve the GMP and the parking alternate (motion moved by Palmasino; second by Dr. Lund). A roll call recorded all present members voting yes; Flynn was absent.

Ending: Administration said phase 1 work will be prioritized so the addition shell can be enclosed during the summer and interior work completed during the following school year; phase 2 remains designed for a later date pending funding and scheduling.