Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Parks And Recreation Center topic
No spam. Unsubscribe anytime.
Bangor City committee reviews updated feasibility plan, asks for cost estimates and pro formas for consolidated parks and recreation center
Summary
A Bangor City special committee reviewed updated design blocks that add a fitness component and refinements to a proposed consolidated parks and recreation facility, requested updated cost estimates and pro formas, and set a timeline for a draft recommendation to go to council by July 10.
Get email alerts on the Parks And Recreation Center topic
No spam. Unsubscribe anytime.
A Bangor City special committee on the proposed consolidated parks and recreation facility reviewed updated design “building program” blocks that add a dedicated fitness area and rearrange other program spaces, and asked project consultants for updated cost estimates, operational pro formas and a phased implementation plan ahead of a July 10 target for a draft recommendation to city council.
The committee met with Barry Dunn, the project consultant, who presented the updated drawings and the list of program areas. "The areas in yellow, they incorporated, the update from the original feasibility study plan," Dunn said, calling attention to a newly added fitness component and reallocation of adjacent spaces. The updated program lists identified a fitness area (labeled 6 in the drawings), a skating center, administrative suites, multipurpose/activity program spaces, an indoor playground and seniors-focused screening/activities in the same block of the design.
Committee members raised questions about site conditions, phasing, renderings and how the new city facility would relate to a large private-sector “Y” project in the same community. Staff reported that a geotechnical firm (SW Cole) completed an initial station 5 test and found the soils “generally favorable,” and that further, more definitive soil borings could be scheduled if the committee wanted them before advancing detailed cost estimates. The consultant confirmed he was in town for an organizational assessment and a facility tour and that the team would produce more detailed renderings and cost updates based on the committee's input.
The committee discussed program and operational choices the design should support: a mix of fee-based fitness membership and open public uses, resident/nonresident fee differentials, dedicated childcare pickup/drop-off and separate childcare entrances, maintenance areas retained in the plan, and a health-care-services block kept as a future potential with appropriate parking. Committee members emphasized accessibility and multigenerational uses — citing seniors' need for indoor winter spaces and community programs — and noted the value of flexible multipurpose rooms rather than narrowly dedicated spaces.
On finance and schedule, Dunn said the consultant team would deliver pro formas showing operating expenses, revenue projections (including fitness membership and rental revenue for ice or other spaces), and examples of potential bonding, sponsorship and naming strategies. The committee asked for f&fe (furniture, fixtures and equipment) estimates and options for phased construction (for example, building a shell that could accommodate fitness equipment later). Documents and the relevant sections of the full master-plan study will be posted on the parks-and-rec project page; the committee requested a consistent meeting invite and agenda distribution and set a schedule of roughly every two weeks to complete work. The committee set an internal target for a draft report to be ready for council packet inclusion by July 10.
Next steps listed by staff and the consultant were: provide updated cost estimates and pro formas, deliver additional renderings (including options for phasing), confirm whether additional geotechnical borings are needed, and post documents to a central project page so committee members and the public can review materials between meetings. The committee will use those materials to produce a staff-assisted draft recommendation that the committee will forward to city council.