Council approves revised change order for water lines supporting Heath Well No. 1

3298393 · May 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

After denying a prior change order, the council approved a revised Hill & Wilkinson change order to install water lines for the City of Heath Well No. 1 project, with staff saying the well is expected to begin producing irrigation water this fall and be potable by early next year.

The Heath City Council on May 13 approved a revised change order with contractor Hill & Wilkinson to install new water lines supporting the City’s Well No. 1 project, after voting to deny an earlier higher-priced change order.

The council first voted to deny a previously proposed change order for $209,601.30. Staff then presented a revised change order for $111,000 and $71.51 (amount recorded in the meeting packet and read into the record), describing a narrowed scope and cost savings after engineering and station identification adjustments. Council approved the revised change order on a unanimous voice vote.

Why it matters: the water-line installation is a critical path item for the well project and for the adjacent park construction. Public Works Director Brian Creed said the lines are needed to allow other contractors (storm-line installers) to proceed without delay. Installing the lines now reduces contractor downtime and associated charges.

Details from staff and council exchange

- Scope: The change order covers both the lines that will feed an irrigation pond within the park and the lines that will route potable-treated well water to a small treatment facility and into a water tower. Creed described the layout: the well will fill a pond on one end for irrigation while other lines run to the tower location where a small treatment facility will be installed before pumping to the tower.

- Production estimates and schedule: Creed said the well’s anticipated raw output is “anywhere from 750,000 gallons a day to a million gallons a day” when fully exercised. Staff told council the original target for water coming out of the well was September 1, but they now expect September 15–20 for raw production; potable use (after treatment and testing, including mineral-content analysis) could be possible by early March of the following year.

- Delay/impact: Councilman Dodson asked how many days were lost while the item moved through review; staff estimated about 20 days lost. Creed said staff had identified areas to reduce haul-off and adjust station identifications that lowered the price from the earlier figure.

- Budget/funding: Creed said the well project is externally funded and that the city remains within overall project contingency margins despite adjustments.

What council decided

- Motion to deny the earlier $209,601.30 change order — approved unanimously.

- Motion to approve the revised Hill & Wilkinson change order for $111,000 and $71.51 to install new water lines supporting Well No. 1 — approved unanimously.

Ending

Staff committed to provide council additional schedule detail (a Gantt chart or milestone schedule) and a clarification of lost days and part-completion dates; council members requested follow-up on activation and milestone dates. The council recorded the approvals as unanimous voice votes.