Council awards East Tripp Road reconstruction contract with fiber conduit option; completion target set to protect school start
Summary
The council awarded a $5,184,909.09 contract to Reliable Paving, Inc. for the East Tripp Road water main reconstruction, asphalt pavement replacement and drainage upgrades; an additive $400,000 conduit alternate for future fiber was included. The contract includes incentives/penalties tied to an August 15 completion milestone for the school year.
The Sunnyvale Town Council on Monday awarded a construction contract to Reliable Paving, Inc. for the East Tripp Road water main replacement, drainage and full-width pavement reconstruction from South Collins Road to East Fork.
The base plus additive bid combined to $5,184,909.09; the additive alternate is a proposed conduit installation for future fiber-optic utilities priced at approximately $400,000 and included as an additive item. Staff reported the design opinion of probable construction cost was about $6.5 million; the lowest responsive bid came in substantially below that figure.
Town engineering staff described the project scope:…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat