Twin Towers expansion progresses: steel up, geothermal equipment installed; district schedules May 29 walkthrough
Summary
District facilities staff reported steady progress on the Twin Towers project: steel erection is underway, geothermal wells and mechanical equipment are installed, foundations and weatherproofing are in place, and a new food-service storage building site has been prepared. A public walkthrough was scheduled for May 29.
District facilities staff updated the board May 8 on construction at Twin Towers and other campus projects, reporting that steel erection is underway, foundations and weatherproofing are complete in multiple areas, and mechanical work linked to a recently installed geothermal system is in place.
The presenters said the project includes three new addition volumes, new electrical service infrastructure, upgraded mechanical systems tied to 85…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat