Contractor seeks nine-month closure of Livingston Road for YMCA-area realignment; city to coordinate notifications and property trade work
Summary
Council was briefed on a plan to close a segment of Livingston Road for full reconstruction tied to an indoor-recreation facility and nearby parking-lot work; staff said the closure would last about nine months, reopen with a binder course and require coordination with the church and a property trade with the sports authority.
Get email alerts on the Road Closures topic
No spam. Unsubscribe anytime.
A planned realignment of Livingston Road near the YMCA as part of an indoor recreation facility project would require a full roadway closure of a segment between Penfield and U.S. 127 for about nine months, staff told the Crossville council.
Tim (staff) said the contractor requested a start date that could be delayed a week for public notification and that the road would reopen before the center opens but with only a binder-course pavement until final asphalt is placed alongside the parking-lot work. “They wanna wait until the final asphalt goes down on the parking lot, at the YMCA before they do that. So it'll reopen with a binder,” Tim said.
Why it matters: The closure affects local traffic patterns for months, requires advance public notice, and ties to a property-trade negotiation involving the sports authority.
Project details and impacts - Closure length and location: Proposed full closure for approximately nine months between Penfield and U.S. 127; target reopening around January (weather permitting). - Pavement staging: Road will reopen with binder pavement; final asphalt will be placed later in coordination with the YMCA parking-lot schedule. - Church/driveway impacts: The church impacted by realignment has been told it will lose its driveway; staff said the church was informed and staff will follow up about the closure schedule. - Property trade: The realigned section will encroach on property owned by the sports authority; staff said they will finalize documents for a property trade and will not complete a trade while traffic remains on the road. - Public notice: Staff recommended delaying contractor start by one week after council approval so the city can advertise the closure to the public.
Next steps Council directed staff to place the road-closure request on the agenda and to continue outreach to the church and adjacent property owners. Staff said they would return with final documents and a public-notice schedule prior to construction.
Ending No formal vote occurred at the work session; staff will present the closure request for formal approval after public notice and final scheduling.