Council approves $426,585 change order for Port Arthur animal shelter after contractor finds buried foundations
Summary
Port Arthur City Council voted May 6 to approve a $426,585 change order to the construction contract for the new animal shelter after contractors discovered unexpected buried foundations and underground conditions; council debated the cost, contingency and schedule extension.
Port Arthur City Council approved May 6 a change order increasing the construction contract for the city's new animal shelter by $426,585.34, citing unexpected underground conditions discovered during excavation that required redesign and additional work. The council also approved a linked budget amendment to cover the increase.
What the council approved Construction Zone (contractor) submitted change order number 1 (actually noted in the packet as change order number 2) to increase the contract by $426,585.34 and to add 214 calendar days to the contract timeline; the new contract total was stated in the staff report as $8,376,034 (construction total) with the revised completion target discussed as October (staff schedule). Council voted to approve the change order and the budget amendment (Ordinance PO7331) that…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat