Ivanhoe water project installs more than five miles of line; contractor projects November 2026 closeout (if on schedule)
Summary
County public works reported 5.4 miles of water line installed recently on multiple roads; contractor timeline shows water services and booster pump delivery late 2025 and project closeout targeted for November 2026 if work proceeds without major delays.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Sampson County public works reported progress on the Ivanhoe water project during the May 20 commissioners meeting, saying crews installed about 5.4 miles of water main in the past month and that the contractor anticipates a November 2026 project closeout if weather and other conditions remain favorable.
Public Works staff (Mr. Kern) listed completed sections and progress: about two miles on McCoy Loop Road, 0.7 mile on Gees Shaw Road, 1.6 mile on Alpine Church Road and 1.1 mile on Hoover Road, for a total of approximately 5.4 miles installed recently. Directional boring crews are continuing work; the contractor provided a timeline that projects water services work to begin in September 2025, arrival and installation readiness of a manufactured booster pump site by early November 2025, flushing and pressure testing in November 2025, and system start-up and booster pump operation in March 2026. Punch-list work and closeout are targeted in late 2026 with contractor documentation estimating November 2026 completion in a best-case scenario.
The project manager said that schedule dependent items (booster pump commissioning, service tie-ins and weather) could extend the timeline and described the contractor's estimate as a 'perfect-world' completion timeline. Staff also reported two grant applications were submitted in late April for water projects on Old Warshaw Road and Mints Highway; the county expects to hear grant results in August or September.
Commissioners and residents asked questions about the Midway Elementary water tower work, which the contractor delayed by approximately two weeks due to equipment malfunction; staff said the contractor expects to place the tower in service within about two weeks of the meeting.
Speakers and procedural notes - Mr. Kern provided the installation totals and the contractor timeline. - The county manager noted staff will update the Ivanhoe community via the county website and direct communications if the project schedule changes.
Why it matters The Ivanhoe water project extends drinking-water infrastructure to multiple roads and communities; timing and grant outcomes affect when households will receive service and the county's capital timeline.