Homes MKE reports 77 homes in process, targets 100–120 before funds expire in 2026
Summary
DCD’s Homes MKE program — originally a $15 million effort to renovate 150 city-held homes — has 77 homes in process and 37 completed; average subsidy per home is about $115,000–$120,000 and staff expect to reach roughly 100–122 homes before rescue-plan funds must be used by mid-2026.
Get email alerts on the Homes Mke topic
No spam. Unsubscribe anytime.
Ed Miller, Homes MKE program lead with the Department of City Development, told the Judiciary and Legislation Committee the program began as a $15 million initiative to renovate 150 homes held by the city. Miller said the program currently has 77 homes in process and 37 fully renovated; of the completed homes, 25 are owner-occupied, six are in lease-to-own arrangements and six are on the market.
Miller said the program’s average subsidy per home is about $115,000–$120,000, which means the original $15 million target will not cover 150 homes; staff now expect to complete roughly 110–122 homes by the program’s end. Miller said developers generally complete rehabs in 4–6 months when resourced; slower firms can take a year or more.
Staff set a hard deadline to use rescue-plan funds by June 2026 so developers can finish and submit invoices. Miller and committee members discussed contractor capacity, general-contractor shortages, and challenges in some properties where repair workbooks produce prohibitively high costs that lead to demolition instead of rehabilitation.
No committee action was taken; staff said they will continue to pipeline properties to developers and monitor completion rates.