After hours of public comment and questions about repair vs. replacement, the council instructed city staff and contractor Grindline to keep the project on schedule while exploring limited design adjustments and options for additional skate facilities.
Get email alerts on the Condon Skatepark topic
No spam. Unsubscribe anytime.
The Grass Valley City Council directed city staff and the contracted designer-builder to move ahead with construction of a new Condon Skate Park while allowing only minor design adjustments that would not delay the project, council members said at a special meeting in City Hall Council Chambers focused on the skate park.
Council members and staff said the decision reflected technical findings from the contractor, community input, grant constraints and the desire to complete construction in a single season. City staff told the council the replacement design is funded by a $1.5 million grant; roughly $100,000 has been spent on design and preconstruction, leaving about $1.4 million for construction and related work.
City staff and Grindline Skateparks presented the project history and the final concept, and Grindline engineer Matt Fligge told the council that the existing concrete slabs at Condon Park are shifting and that repairs are likely to be temporary. "When a skate park is either near or at the end of its lifecycle, repairs are just that — repairs," Fligge said. He added, "most of us probably heard the term ‘lipstick on a pig,’ but that's what we literally would be doing here to sort of repair this existing skate park."
Grindline and city staff described the procurement and outreach timeline: a request for proposals issued in November 2023 produced three respondents; Grindline was selected and a kickoff meeting and community input meetings were held in April, June and July 2024. Grindline completed a geotechnical report and submitted final construction drawings for staff review. The final approved concept reduces the skateable concrete footprint from about 23,000 square feet (the existing layout outside the fence) to roughly 15,000 square feet for the new design, city staff said.
Many speakers at public comment urged the council to preserve and repair the existing Condon Skate Park rather than demolish it. Speakers cited community history, safety for different user groups, and petitions gathering signatures to keep or rehabilitate the existing facility. A teacher who skated with students at the site said several students had been injured on the cracked surface. One public commenter said a petition had grown to more than 800 signatures; other speakers asked the council to commission an independent engineering review before demolition.
Council discussion focused on three constraints: the technical assessment from Grindline and its engineers that the slabs are moving and drainage beneath the park needs substantial rework; the funding and timeline tied to the grant (city staff said all grant-funded work must be completed and invoiced by 2028); and procurement/contract realities tied to the design-build agreement with Grindline. City staff and the contractor warned that changing the project location or restarting design would trigger additional geotechnical and topographic work, a longer environmental review in some scenarios and likely additional cost and delay.
Council members acknowledged those concerns while also expressing the community's desire for a larger or different layout. Several council members urged staff to look for additional parks or funding sources to add skate facilities in other locations in Grass Valley. One council member summarized the council's consensus at the end of the meeting: proceed with the current schedule and contract while asking Grindline to evaluate only minor adjustments that will not alter grading, drainage plans or the construction timeline.
The meeting record shows no formal roll-call vote on a motion to change the contract; instead, council direction to staff and the contractor was recorded as the outcome of the discussion. Staff said the city can pursue future expansions or an additional skate park if the council wishes, and noted potential funding sources such as future cannabis grant rounds and Measure E matching funds.
What happens next: the contractor's construction documents will move toward permitting and mobilization. Council members and staff encouraged continued community engagement, and staff agreed to explore possible additional skate facilities and fundraising options that would not disrupt the current construction timeline.
Notes: The city emphasized that the final construction schedule aimed to complete the build in a single construction season to minimize the time the park is unavailable to skaters. Several speakers asked for a third-party evaluation before demolition; council members asked staff to consider the feasibility of additional outreach while keeping the project on track.