Summary

The Heath City Council approved a preliminary plat for a 10‑lot single‑family subdivision on the southeast side of FM 549 with four conditions including a traffic impact study and a requirement that the domestic water be a loop system.

Heath City Council on April 22 conditionally approved a preliminary plat for a proposed residential development of 10 single‑family lots on a 14.614‑acre tract on the southeast side of FM 549.

The item, presented by city planning staff member Mr. Gonzales, came after the property was rezoned last year from agricultural to a planned development district. The council approved the preliminary plat with four conditions: complete the applicant statement on the submittal, perform a traffic impact study with consideration of a turn lane, investigate potential on‑site water use for irrigation (including the detention ponds, a possible spring or cistern), and require the domestic water distribution to be a loop system rather than a dead‑end flushing system.

The nut of the application is the concept approved in the prior zoning action: 10 single‑family lots in a Planned Development (Zone 4, PDSF) served by a new 13‑50 foot roadway and a cul‑de‑sac. Mr. Gonzales told the council the lots meet dimension standards, have access to water and sewer, and that the submitted tree plan showed removal of 40 trees (totaling about 340 inches) with mitigation planting of 93 replacement trees. "They are netting the mitigation out to 0," Mr. Gonzales said, and staff concluded the tree scape plan met the city requirements.

Council members pressed the applicant and staff on specific infrastructure and documentation. Councilman Dodson and others asked for a traffic impact analysis and consideration of a turn lane from FM 549, noting the roadway is currently two lanes and could later be expanded to four. The council also raised water‑system questions: staff noted the preliminary documents included a proposed dead‑end 8‑inch water line with an auto‑flush connection; several council members said the city policy is to require looped domestic water lines where feasible. The council voted to make the loop requirement an explicit condition, and directed that the loop be achieved before final plat approval, which may require easements to neighboring properties.

Council members also queried the applicant about using on‑site detention ponds or an old cistern/spring for irrigation via reclaimed or purple‑pipe systems; the applicant said the engineer had previously discussed the possibility but that details were not included in the current preliminary plat package. Staff said notices were sent at the zoning stage but that plat approval is a ministerial action under state law and does not trigger the same notice requirements.

Planning & Zoning had recommended approval on April 1. City staff noted a fee‑in‑lieu calculation for park land and development fees: for the 10 lots the packet lists a total fee of $35,401.30 to be paid with the final plat and deposited into the park fund. Councilman Shaw (speaking during the hearing) asked staff to verify an apparent discrepancy in the compliance matrix showing 0.6 acres of public/open space when the plat itself shows two open areas totaling 1.4 acres; staff agreed to verify and correct the documentation if needed.

After discussion and the four conditions stated on the record, the council voted to approve the preliminary plat; the motion passed unanimously. The item will return as part of the final plat process, at which time the council and city engineering will verify that required conditions (traffic study, water loop, irrigation feasibility, and completed applicant statements) have been satisfied.

The council also noted additional administrative items related to the development — street‑name review with 911 dispatch and building‑permit review for garage orientation at the time of construction — will be handled during subsequent permitting steps.