Wagoner council approves $4,320 change order for Lincoln Park pickleball court
Summary
At a special meeting April 20, the City of Wagoner Council approved Change Order No. 1 — a $4,320 addition — to install a moisture barrier under the Lincoln Park pickleball court after contractors found moisture issues that prevent paint from adhering to the surface.
Get email alerts on the Parks Play Surfaces topic
No spam. Unsubscribe anytime.
The City of Wagoner Council approved a $4,320 change order on April 20 to add a moisture barrier under the concrete base of the Lincoln Park pickleball court, after contractors found moisture rising through the slab that would prevent surface paint from adhering properly.
The extra work was recommended by Infrastructure Solutions Group LLC and described to the council as a necessary step to prevent bubbling and premature paint failure. “What this is is we thought we were gonna be able to paint those pickleball court. It's not gonna be able to adhere with the moisture coming through. So this is putting down a moisture barrier under the concrete,” Gary Recker said while presenting the parks estimate and options.
The council discussed warranty and durability. Staff said the installation of the moisture barrier and subsequent work would carry a one-year warranty on the installation; there is no warranty on the paint. Council members expressed concern about recurring change orders and about whether the project had been bid with the correct scope initially. One council member noted that change orders are the mechanism contractors use when a site condition requires additional work beyond the original bid; another said the barrier could substantially lengthen the time before resurfacing would need repair.
Councilors then moved to approve the change order. The motion and second were recorded in the meeting minutes, and the roll call vote was: Higginbotham — Yes; Sampson — Yes; Wagner — Yes; North — Yes; Thomas — Yes; Wilson — No; Wright — Yes. The motion carried and the change order was approved.
No additional funding source beyond the change order amount was specified in the meeting record. Council chair noted the item had not been previously approved and that the change order required council approval before the contractor proceeds.
The meeting moved on to discussion of the city's fiscal year 2025–26 budget after the vote.
Votes at a glance: - Change Order No. 1 for Lincoln Park Pickleball Court improvements (infrastructure recommendation by Infrastructure Solutions Group LLC): approved, tally Yes 6, No 1.
Notes: The record indicates the warranty on installation is one year; staff explicitly said there would be no warranty on the subsequent paint layer.