UOG updates on new buildings, sanitary-permit compliance and IT savings from VoIP project
Summary
Facilities staff reported construction progress on four new buildings, a campus sanitary-permit compliance effort with estimated $230,000 of fixes and projected savings from a new VoIP system to support other IT upgrades.
Get email alerts on the Campus Construction topic
No spam. Unsubscribe anytime.
The Board of Regents received a facilities update April 24 that covered construction progress on four new campus buildings, a sanitary-permit compliance process and planned IT infrastructure changes designed to free funds for modernization.
Regent Pete Diaz, reporting for the Physical Facilities Committee, said facilities management has identified campus maintenance items that must be addressed to meet a sanitary permit requirement, listing an estimated $230,000 of repairs ranging from cracked tile to paint chips. Diaz said the university is working with deans and administrative officers to prioritize and implement fixes.
Construction status for major capital projects reported to the board:
- Student Success Center: 73% complete; expected substantial completion in August 2025. - School of Engineering: 91% complete; target completion June 2025. The school is seeking additional funding for furniture, fixtures and equipment. - Water Environment Research Institute (EDA project): 46% complete; expected completion October 2025. - School of Health: 47% complete; expected completion October 2025.
Diaz said the university issued a bid for a new VoIP communications system and projects roughly $340,000 in savings from the replacement. The plan is to repurpose those savings for IT modernization work such as cabling, servers and applications, Diaz said. Facilities staff answered committee questions to the committee members' satisfaction, according to the report.
Direct quote
"FMS has been working with the deans, the administrative officers, and looking to all the little items that are all around the campus ... They've, you know, tallied up, dollars 230,000 worth of those fixes," Regent Diaz reported.
Context
The four projects are the major elements of the university's recent capital expansion and were discussed repeatedly in committee updates during the spring. The board noted continued need for funding of furniture, fixtures and equipment for the new facilities and ongoing procurement and contracting activity tied to the construction work.