Board approves CMAR RFP process for high‑school/middle‑school renovations and turf projects
Summary
Smithville R‑II approved the construction manager-at-risk (CMAR) request-for-proposals process for multiple renovation projects, including high school and middle school work and athletic field/turf jobs. Staff described options bidders will provide and the schedule for selection.
Get email alerts on the Construction Procurement topic
No spam. Unsubscribe anytime.
The Smithville R‑II Board approved the release of construction manager-at-risk (CMAR) request-for-proposals (RFPs) for the high school and middle school renovations, baseball/softball renovations and turf projects.
Staff said the RFP package will be released promptly and described the procurement approach: three firms will be solicited for the high school and middle school renovations, two of those firms also bid on baseball/softball renovations, and four firms will be solicited for baseball/softball and elementary turf work. The board was told the high school/middle-school proposals will include a per‑square‑foot cost option while the baseball/softball work is structured as a turnkey proposal; firms were asked to provide estimated budgets for each option.
Dr. Newhart and other administrators summarized the review process: cabinet members and invited staff reviewed RFQs and RFPs and a schedule is included in the packet. Staff emphasized the CMAR approach gives contractors "skin in the game" and that guaranteed maximum price (GMP) negotiations will follow selection. The RFP documents include standard AIA attachments and will be legally reviewed before final contracting.
Action: The board moved, seconded and approved the RFP process as presented; staff will issue the solicitation, field bidder questions, and share responses with all prospective firms.
Why it matters: Approving the CMAR RFP advances design-to-construction procurement for significant renovation and athletic-field projects and sets the procurement method and schedule for contractor selection.
Implementation: Staff said they will publish the RFP, host question periods, circulate responses to all bidders to ensure parity, receive proposals, and return to the board for selection and GMP negotiation.