Commission approves EMS roof work; EMS monthly report received
Summary
The commission awarded a $20,476 contract to Trower Roofing for an EMS building roof restoration and received the March 2025 EMS report; officials said the roof work will be paid from reserve funds and include a 10-year labor and 20-year materials warranty.
Get email alerts on the Facilities Ems topic
No spam. Unsubscribe anytime.
The Atchison County Commission approved a contract with Trower Roofing & Coatings to restore the metal roof of the county EMS building at 10443 US Highway 59. The contract price is $20,476 and includes a 10-year labor warranty and a 20-year non‑prorated materials warranty.
Maintenance director Brian Oswald presented two bids: Trower ($20,476) and BRT ($36,960). Commissioners approved Trower’s proposal and directed that the work be paid from county reserves because the repair addressed unexpected water damage.
Corey Scott, EMS director, presented the March 2025 EMS report; commissioners voted to receive and file the monthly report.
Why it matters: The roof repair is intended to stop ongoing water intrusion and preserve the county-owned EMS facility; the warranty terms were emphasized as part of the motion. Commissioners noted reserve-use and scheduled the project to proceed.
Ending: Staff will execute the roofing contract and schedule the work; the EMS report will be included in routine filings.