Ranch Heights construction on track; district lining up summer projects at all sites

3074861 · April 22, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District staff reported punch‑walk completion at Ranch Heights, advanced elevator scheduling and plans to start moving classrooms around May 1; principals submitted summer project requests and the district is ordering materials to begin summer work.

District staff reported progress on construction at Ranch Heights and described planning for summer maintenance and renovation work across schools.

Staff said a punch walk in the new safe‑room area at Ranch Heights occurred two weeks earlier and that classroom finishes looked good. The district advanced the elevator start date to compress lead time and said site work — including asphalt — was scheduled to begin but could be affected by recent rain.

District staff told the board they expect to begin moving classroom materials into new pre‑K and kindergarten spaces around May 1, using a staged move similar to the Wayside school transition. The move sequencing, staff said, will allow classrooms to be set up in the new areas before summer interior work begins.

On summer projects, principals compiled top four to five requests per site. The district is pricing materials and considering in‑house work by Sodexo maintenance staff for some projects. Examples cited included building a wall in an IT closet and installing dimmable lights in a special‑needs classroom; the district said crews performed some of those items over spring break to get ahead.

Staff identified Kyle Hendricks as maintenance supervisor and said he will serve as a primary contact during the upcoming transition. No board action was required; the report was informational.