Commission approves CIP adjustments and design contract for courthouse remodels
Summary
The commission approved updates to the county’s capital improvement plan, added a design project for a range/classroom at the security center, and approved a contract with Galloway & Company to design remaining remodels of the county administration building; staff said using vacated space could shorten a multi‑year remodel schedule.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The Utah County Commission on April 19 approved changes to the county’s capital improvement plan (CIP) and a contract with architectural firm Galloway & Company to complete design work for remaining remodels in the county administration building.
Why the vote matters: County staff said the adjustments reflect updated bid pricing, change orders and 2023 actual expenditures; the update also adds a new design-phase project for a classroom/training facility at the Thistle gun range (security center), with construction expected in 2027 if funded.
Staff overview: Richard Nelson, the county’s public-works director, told commissioners Galloway submitted a price to design remodels on the first through third floors of the administration building. The county has completed the recorder’s office on the first floor and HR on the third floor and is finishing a portion of the attorney’s office on the second floor. Nelson said using recently vacated space in the Health and Justice Building could allow the county to do two remodels at a time and shorten an estimated three- to four-year schedule.
Budget and new project: Rudy Livingston, deputy auditor and chair of the CIP committee, said the committee brought the adjustments to avoid repeating prior budget shortfalls related to inflation and bid increases. Staff presented a simplified spreadsheet showing changes; the county reported about $160,000 of currently unallotted CIP funds, and officials said many line items were reconciled to 2023 actuals and updated cost estimates.
Regulatory and design details: Nelson said the remodel work will include restroom updates to comply with new state rules on single‑use restrooms in public buildings. The added security center gun‑range classroom project is currently budgeted for design only, with construction planned for 2027 pending funding.
What the commission approved: Commissioners approved item 23 — the design contract with Galloway & Company for the administration building remodels — and item 19 — the CIP revisions and project updates. Commissioners said staff will return with the 2025–34 CIP later this year and that project timing depends on availability of temporary space and funding.
Quotes: “We need to bring things back to you because we do not want to get into a situation that we were in a year or so ago where hyperinflation just blew all of our projections,” said Rudy Livingston, deputy auditor and CIP committee chair. Richard Nelson said using vacated Health and Justice Building space could “cut that time in half” if the county can house displaced offices temporarily.
Next steps: Staff will continue reconciling project costs, coordinate temporary relocations, and return to the commission with the broader CIP schedule and final designs.