District updates construction timeline; board approves high school restroom renovation bids
Summary
District staff and contractors updated the board on multiple facilities projects — Central community center pool and locker renovation, Aquila addition and remodel, high school stadium and turf replacement — and the board approved high school restroom renovation bids 7-0.
Get email alerts on the Facilities Construction topic
No spam. Unsubscribe anytime.
St. Louis Park Public School District staff and construction contractors briefed the school board on ongoing and upcoming capital projects and the board approved bids for a high school restroom renovation with a unanimous 7-0 vote.
Presenters described progress at the Central community center (locker-room and pool renovation), the Aquila addition and remodel (about a 15,000-square-foot addition with four kindergarten classrooms, new cafeteria and storm shelter), and high school stadium work including bleacher removal, new ADA-compliant seating, team rooms and turf replacement. Staff and contractors said the Central pool mechanicals and new ADA pool lift are installed and that pool and locker-room work is nearing completion; they estimated pool and locker rooms would be operational roughly a week after July 4, with substantial completion of broader Central community center work targeted for Aug. 29.
On Aquila, contractors described a phased plan that prioritizes interior renovations and special-education quiet rooms so classrooms and key spaces will be ready for the start of school; interior work and outfitting were projected to be substantially complete for fall with a certificate of occupancy targeted in October and a staged move of classroom furniture and technology in November, with students using the new spaces after winter break and a target of Jan. 5 for full student occupancy in the new gym area. The project includes a precast-panel storm shelter and new kindergarten classrooms and Kids Place space; contractors said construction sequencing was adjusted to avoid overtime and weekend work that would substantially increase costs.
Contractors said crews are already dismantling the high school home-side bleachers and installing storage and team-room spaces beneath new seating; they noted the existing turf had exceeded its expected life and crews are recycling the turf infill for the new field. Presenters said the stadium work will improve accessibility and provide railings and designated areas for spectators using wheelchairs.
The board then considered and approved bids for the high school restroom renovation project. District staff said bid pricing for the restroom work came in about 15% higher than anticipated but recommended proceeding; the motion to approve passed unanimously.
Clarifying details provided at the meeting included projected substantial-completion dates (Central: Aug. 29; Aquila certificate of occupancy targeted for October; staged move and student occupancy after winter break/Jan. 5 target), Central pool and locker rooms operational roughly a week after July 4, and that the Aquila addition is roughly 15,000 square feet. Contractors described trade-offs made in design (for example, scaling back a two-story clerestory in the Aquila cafeteria to meet schedule constraints).