Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Shockoe Heritage Campus topic
No spam. Unsubscribe anytime.
City presents plan, funding and timelines for Shockoe heritage campus including Lumpkin’s Jail pavilion
Summary
City staff presented an updated plan and funding overview for the Shockoe heritage campus, including Lumpkin’s Jail pavilion, exhibit hall, Anne Carroll’s Landing and Slave Trail improvements, and burial-ground commemoration.
Get email alerts on the Shockoe Heritage Campus topic
No spam. Unsubscribe anytime.
City staff presented an updated plan and funding overview for the Shockoe (heritage) campus, a multi-element program that includes a Lumpkin’s Jail pavilion, Anne Carroll’s Landing and Slave Trail improvements, relocation and restoration of the Emily Winfrey cottage, the Shockoe Institute exhibit hall, a Shockoe Hill African Burial Ground commemorative space, and a proposed National Slavery Museum.
Presenter Ms. Ebert said the Shockoe Institute — a nonprofit partner that received Mellon Foundation grant support — is contracting exhibit design and that the city has engaged Baskerville as lead designer for a 12,000-square-foot exhibit hall. Ebert said the Baskerville contract to design the exhibit hall is approximately $986,948 and that Team Henry has a construction award of about $2,500,000 for build-out work. The exhibit build-out was described as beginning in spring with a timeline of roughly 12 months to opening in summer of the following year.
Ebert detailed the Lumpkin’s Jail site, noting archaeological remains found about 10–15 feet below grade, and described a pavilion and design that would allow visitors to view excavated foundations and interpretive materials. She said the Lumpkin’s pavilion construction estimate is about $17.5 million and that the broader southern-campus element, including the South Memorial, has a current estimated cost of about $34 million. Ebert said the city had secured a combination of state funding ($13.4 million noted) and city capital budget allocations and that, in total, roughly $32 million was budgeted in the city’s Capital Improvement Program for Shockoe project elements, with an additional $10 million budgeted in fiscal 2026–27; Ebert described total available funding for the initial listed elements at about $45 million.
Ebert described the Emily Winfrey cottage relocation and restoration — estimated at about $1.5 million and included in the CIP — and the Anne Carroll’s Landing and Slave Trail work (contract award to Team Henry at roughly $2,000,000). She said moving the cottage is a prerequisite to starting Lumpkin’s Pavilion construction and that rights-of-way across CSX Railroad have been a permitting challenge for the Slave Trail improvements. Ebert also said the city purchased a 1.2-acre parcel that contains the Shockoe Hill African Burial Ground and that the city successfully had it designated as a cemetery; the estimated budget for commemorative improvements on that 1.2-acre parcel is about $1.8 million.
On the National Slavery Museum, Ebert said the city is cooperating with a foundation that plans to fundraise for a museum; she said the museum is not in the city budget and estimated the likely construction cost “well over $100 million.” She acknowledged floodplain and stormwater constraints across the site and said some design elements, including a bridge over East Broad Street, address floodway mitigation.
Council members thanked staff and requested follow-up questions; staff said they would be available for more detailed conversations on design and implementation.
