Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Public Works topic

No spam. Unsubscribe anytime.

Council approves pay application for Cascade Public Library, withholds $10,000 for exterior work

3141189 · April 28, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The city approved pay application No. 15 for the Cascade Public Library project, but the council will withhold $10,000 pending satisfactory completion of exterior work, including final grading and seeding.

Cascade City Council approved Resolution 44-25 on Monday to authorize pay application No. 15 for the Cascade Public Library project while withholding $10,000 in retainage for outstanding exterior items.

City staff told the council that the engineer, architect and contractor disagree about responsibility for finishing work near the library entry, where the soil remains sandy and gravelly. Staff recommended paying the application but holding $10,000 until agreed remedial work is completed.

Councilmember Oliphant moved to approve pay application No. 15 with a $10,000 correction to the retainage amount; the motion was seconded by Councilmember Hush and passed on a roll call that recorded unanimous "aye" votes.

Staff noted the project warranty/bond period is two years, during which the contractor is responsible for fixing issues that arise. Councilmembers asked staff to monitor the remaining punch list items and report back if further action is needed.