Wold Architects presented an interim space-needs and facility-condition assessment showing major usable-space shortfalls in the courthouse, district attorney and courts, and Health & Human Services, and recommended a prioritized multi-year master plan.
Get email alerts on the Facility Planning topic
No spam. Unsubscribe anytime.
Wold Architects presented mid-study findings of a countywide space needs and facility condition assessment to the Ashland County Board of Supervisors, identifying substantial shortfalls in usable office and meeting space across multiple county departments.
The firm's lead, Jonathan Lause, said the study compares existing usable square footage (USF) with projected needs based on department functions and industry benchmarks. The courthouses' usable area was estimated at about 4,000 USF with a projected need near 7,100 USF; Health & Human Services was cited as operating at about 6,600 USF with a projected need of about 16,000 USF; the sheriff's office and jail showed a projected increase from roughly 18,000 USF to 27,000 USF. Lause also identified building-condition issues in the courthouse, including water damage, noncompliant toilet rooms, a lack of fire protection, and security and circulation concerns during court hearings.
Lause presented a set of guiding principles developed with a county core planning group: create appropriate workspace to allow optimal workflow and future growth; provide shared and public meeting spaces; retain the historic courthouse when feasible; address safety and security needs; and follow a fiscally responsible, phased 20-year master plan. He said the next step is to develop and cost alternative facility-response options and timelines for the board and core planning group to review.
Board members raised possible site and operational considerations. One supervisor suggested evaluating remote county-owned properties (for example, in Moringo/Highbridge areas) as alternative locations for departments such as land conservation to reduce travel for field staff and consolidate storage. Another asked whether the study would recommend operational efficiencies and internal reassignments; Lause said the firm's role includes department interviews and cross-department analysis to identify efficiencies and options, which will be reflected in the options phase.
The county will receive a full report that itemizes current conditions, room-by-room space calculations, priorities and recommended phasing, and preliminary cost estimates. The board did not take a vote on the study at the meeting; Wold Architects said they will return with options and cost estimates for future board consideration.