Zoning board grants second 12‑month extension for 169 Wellington Ave. pool project

3142299 · April 28, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board granted a second 12‑month extension for construction at 169 Wellington Ave., citing financing and contractor delays; the applicant had completed the pickleball court but has not yet found a pool contractor.

NEWPORT — The Newport Zoning Board of Review granted a second 12‑month extension on April 28 to the owner of 169 Wellington Ave., allowing more time to start construction of a previously approved pool.

The board heard from the applicant’s attorney, who told the panel the project has been delayed by financing and difficulty finding a pool contractor; the site’s pickleball court portion has been completed. The attorney said the owner still intends to proceed with the pool but has not secured a suitable contractor.

"It's really just a matter of financing," the attorney said, explaining the delay and confirming a suitable pool contractor had not yet been found.

Why it matters: This is a second 12‑month extension to the property’s prior zoning approval. Approvals include conditions the board repeatedly applies: work must begin and be substantially complete within the extension period, or the applicant must request further relief from the zoning officer before expiration.

Board action: The board voted unanimously to grant the extension. The decision includes the standard conditions: the applicant must begin and substantially complete the project within 12 months of the decision or request an extension from the zoning officer prior to expiration, and all outstanding public-noticing invoices must be paid before the decision is recorded.

Next steps: The applicant must secure financing and a contractor and proceed to building‑permit review. The board’s extension will expire April 28, 2026, unless further extension is requested and granted.