Board approves change orders for Muhlenberg middle-school field house; water-line replacement and dugout work included
Summary
The Muhlenberg County Board approved multiple change orders to address unforeseen site conditions at the middle-school field house project and to replace aging utilities and damaged structures, including replacement of an old PVC water line and temporary fixes to dugouts and a press box.
Get email alerts on the Facilities Construction topic
No spam. Unsubscribe anytime.
The Muhlenberg County Board of Education approved a series of change orders for the Muhlenberg County Middle School field-house project and related athletic-facility repairs after staff reported unforeseen site conditions and storm damage.
Facilities staff described additional sinkholes, drainage problems and brittle underground water lines that were discovered during construction. The board approved change order No. 1 to address sinkholes and drainage work and approved change order No. 2 to remove and replace a brittle 3-inch PVC water line back to the existing middle school. Staff said replacing the full run is preferable to repeatedly repairing failures in old pipe.
Change order No. 3 covers replacement and related work for a press box and dugouts that were demolished by wind; staff said the originally supplied paperwork contained a clerical error with extra zeros and the board authorized approval while paperwork is corrected for signature.
Board members discussed interim safety measures for the baseball facility; staff said a temporary fence is installed and that a new dugout will be designed, though not in place for the current baseball season. The board approved the change orders by voice vote.
Facilities staff also described a broader set of renovation projects around the district—which are being value-engineered in some cases—after bids for some school projects came in significantly over initial target budgets. Staff said architects and contractors are working to reduce costs by altering finishes and some nonessential space so projects can align closer to budget targets.
Motions to approve the three field-house change orders passed on voice votes during the meeting and staff said they will return corrected paperwork for signature.