Gates County utility staff report meter replacement progress, $3.2M utility fund balance and possible capital requests
Summary
County utilities staff updated commissioners on a large meter-replacement program, contractor data upload problems, increased revenues from new meters and a utility fund balance; staff said a capital request for well/pump upgrades may be forthcoming.
Get email alerts on the Public Utilities topic
No spam. Unsubscribe anytime.
Gates County public utilities staff briefed the county board on progress of a multi-year water‑meter replacement program, contractor data issues and the county's utility fund position at the April 3 special meeting.
Staff said the utility fund ended the most recent year with roughly $3.2 million in working capital. They reported the county has been replacing old manual meters with newer automated meters and that the new metering has increased measured water sales — an increase staff estimated at roughly $600,000 (approximate figure provided by staff) — which they said should improve revenue recognition and reduce lost water from unmetered use.
Why it matters: Commissioners heard that the meter conversion supports the county’s goal of returning to a monthly billing cycle (the target date discussed was July 1) and that the conversion should make revenue and demand accounting more accurate. Staff also warned the board the meter‑installation contractor delivered mis‑matched serial/EID codes in some uploads; the error will require audits or corrections on the back end for several hundred meters and will slow the pace of returning to monthly bills.
Staff said 611 meters remained to be installed and 800–1,000 meters had data that likely need correction in the billing system. That backlog will require manual auditing of individual meters and corrections before full monthly billing resumes, staff said. Commissioners were told a rate study is typically done every four to five years and that no immediate rate increase was anticipated for the current fiscal year.
Staff also previewed an upcoming capital request that could be made to draw on the utility fund for well and pump upgrades and replacement of meters and other equipment; commissioners asked for a formal presentation with cost estimates and revenue impacts before any draw on the fund.
Ending: The board asked utilities staff to bring a formal capital request with cost estimates and to document the meter‑conversion progress, the contractor corrections needed and the expected revenue impact prior to any rate or fund transfers.