Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

District updates timeline for Woodland Jr. High mass-timber build, FHS parking deck and John L. Covert work

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Operations staff reported the Woodland Junior High site and early MEP packages are permitted and on track, with building work to begin summer 2025 for completion targeted for the 2027 school year; FHS parking-deck and John L. Covert conversion projects also on schedule for summer starts.

Steve, the district maintenance and construction director, gave a construction update at the April 24 meeting covering three major capital projects.

Woodland Junior High: Steve said the Joyce Road extension grading permit and the building-site grading permit were approved and that contractors should begin site work the week following the meeting, weather permitting. An early…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans