Goshen planning board grants six-month extension for SR 94 LLC solar project
Summary
The Goshen Planning Board approved a six-month extension for conditional site plan approval for the SR 94 LLC solar project, moving the deadline to Nov. 6, 2025, after an extension request submitted April 21, 2025.
Get email alerts on the Solar Permitting topic
No spam. Unsubscribe anytime.
The Goshen Planning Board voted to grant a six‑month extension for the SR 94 LLC solar project, moving the deadline for conditional site plan approval to Nov. 6, 2025.
Olivia Feldman, who signed an April 21, 2025, letter to the board as the applicant’s development manager, requested the extension and said the applicant was cooperating with the town and expected to satisfy outstanding conditions. The letter referenced correspondence from Sean Hoffman on April 18, 2025, and noted the conditional site plan approval was due on or about May 7, 2025.
Town counsel and the board discussed the request briefly. A motion to grant the six‑month extension was made and approved by voice vote; no opposing votes were recorded. The board recorded the new target date of Nov. 6, 2025 for the SR 94 LLC conditional site plan.