Supervisors approve awards and change orders for multiple county road projects
Summary
The Oktibbeha County Board of Supervisors accepted contractor bids, approved a change order to add Bluff Lake Road to an existing Blackjack Road contract and authorized awarding a District 2 construction contract, with board members saying the approvals keep projects within available funding and allow phasing of work across contractors.
Get email alerts on the Transportation Roads topic
No spam. Unsubscribe anytime.
Oktibbeha County supervisors voted to proceed with several road contracts, advertise bids for additional work and approve a change order to add Bluff Lake Road to the Blackjack Road contract.
The action followed discussion of a spreadsheet of roadway estimates and contractor bids. Supervisors approved setting a bid date for several smaller road segments and asked staff to prepare a change order to add Bluff Lake Road to the Blackjack contract; the board directed that the same contractor who is already under contract for Blackjack would handle the added work.
The board discussed an estimated change-order amount for adding Bluff Lake of $228,630.05 and staff said the county has funding available when accounting for annual road-plan allocations and upcoming receipts. Supervisor comments described a plan to manage the District 2 package so total work remains under the county cap discussed by board members (approximately $2,000,000 in aggregate for the package) and to use change orders and schedule adjustments to keep work within that envelope.
Supervisors also moved to award a separate District 2 construction contract to Fit Construction (award motion made during the meeting). Board members said they will use change orders and set-asides from other projects to keep the total within available funds and will phase certain work to maintain construction continuity.
During the meeting staff said some roads will be bid together because they are simpler and are easier to manage as a single contract; other roads (Clifford, Jordan and Ballard) will be bid as separate projects so the county can employ two or three contractors simultaneously to keep work moving. Supervisors asked staff to prepare contract documents, advertise the adjusted bid packages and return executed change orders for signatures.
Board discussion also covered material choices and a soil-cement pilot on Cannon Road and Brooksville that staff said had performed well in a recent trial; officials described the product cost (about $55,000 material estimate for a pilot) and a contractor service bid of roughly $29,000 for installation on a prior job. Staff said the county will supply shaping and paving labor where schedules permit.
Votes at a glance - Motion to advertise bids for specified road segments and set a bid date: motion carried (motion recorded; vote announced as passed). - Motion to prepare and return a change order adding Bluff Lake Road to the Blackjack contract (estimated $228,630.05): motion carried; staff to bring change order back for signature. - Motion to award District 2 contract to Fit Construction: motion carried; board directed staff to proceed and to manage funds via subsequent change orders.
Why it matters Road maintenance and resurfacing are the county's primary capital activities discussed at the meeting; the board's actions set procurement timelines, obligate funding for specific contractors and shape the sequence of construction across multiple districts.
What’s next Staff will prepare the formal change order documents and contract awards for board signatures and will return on a future agenda with the executed change order(s) and final tabulations for the advertised bid openings.