Madison County project to widen two bridges at Andor Road–North Old Canton Road intersection moves into right‑of‑way phase
Summary
Benchmark Engineering told Madison County officials the Andor Road at North Old Canton Road intersection project will widen two bridges (Yandell Road and North Oak Canton Road), realign a stream to reduce scour, and begin right‑of‑way acquisitions for about 10 parcels as environmental studies continue.
Get email alerts on the Transportation Infrastructure topic
No spam. Unsubscribe anytime.
Lon Burt, with Benchmark Engineering and Surveying, updated Madison County meeting attendees on plans to widen two bridges and rework the Andor Road at North Old Canton Road intersection, saying the project is moving toward right‑of‑way acquisition while environmental reviews continue.
Burt said the project includes bridge replacement and widening work for two bridges — one on Yandell Road and one on North Oak Canton Road — plus intersection improvements. “We're currently working on field review plans for the intersection as well as bridge replacement and widening plans for the 2 bridges, 1 on Yandell Road and 1 on North Oak Canton Road,” Burt said.
The Yandell Road bridge will be widened from an existing 28‑foot span to just under a 90‑foot span, including shoulders, to meet federal and MDOT design standards for an LPA project, Burt said. (The meeting transcript used the abbreviation “MDOT”; the agency was referenced in the presentation.) Burt said wetlands and other waters reporting has been completed, cultural studies were expected to begin the week of the update, and the project team had requested an extension on an environmental deadline. He said environmental work is expected to be completed this year, by December if possible.
Burt said the project team expects to have bridge plans ready to advertise within the next reporting period, to hold a field review meeting with MDOT on the intersection portion, and to begin right‑of‑way acquisition. He told the meeting the board packet included a supplemental agreement related to right‑of‑way work. Burt said the team currently anticipates acquisitions affecting about 10 parcels, and that those parcels have mixed zoning (transcribed in the meeting as “a 1, c 2 and residential zoning”).
The presentation also covers a planned stream realignment near the two bridges to reduce undermining and scour where the existing stream currently turns 90 degrees at North Old Canton Road. Burt said the realignment is meant to lessen scour and undermining that the existing geometry is likely to exacerbate when bridges are widened.
A staff member asked whether the road would be kept open during bridge work. Burt said the team has considered constructability and discussed either phasing the bridges or using a short detour at the intersection, and confirmed there are plans to avoid a prolonged full closure. A resident asked the project team to “please have a way for people to keep traveling,” expressing concern about access during construction.
No formal motions or votes were recorded in the transcript excerpt provided. The presentation outlined design milestones, environmental work, the anticipated right‑of‑way phase and alternatives for maintaining traffic during construction.
The project remains contingent on completing environmental reviews, the MDOT field review and right‑of‑way acquisitions before construction can proceed. The county and consultant expect to advertise bridge plans and continue coordination in upcoming reporting periods.