Marina manager updates council on dry-storage building progress and schedule

5870245 · July 23, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Marina staff reported progress on the dry-storage building foundation and that metal building erection is expected in September; a $97,000 credit reduced some foundation costs and staff confirmed contingency remains.

The marina manager briefed the council on the dry-storage facility construction and project status.

Progress and schedule Staff reported the West deck pour and other foundation work were scheduled, with a large concrete pour planned and the intent to begin metal-building erection in September. Some delays occurred when a transition piece for the pour did not arrive on time; staff said the schedule has enough slack for the adjustment.

Cost and contingency Contract adjustments produced a credit of roughly $97,000 by reducing auger-cast piling; staff said this reduced foundation costs and improved contingency. The council reiterated that underground work is substantial and that building erection will proceed quickly once components arrive.

Next steps Marina staff said they will continue to coordinate on site deliveries, complete foundation pours, and start above‑grade metal building construction in late summer or early fall. Council asked staff to keep the council informed of any material changes to cost or schedule.