District delays final contractor payment pending water-line alignment resolution; punch‑list walk‑throughs continue
Summary
District staff reported punch-list work nearly finished on Rollins and Tuscher projects but said final payments may be held while staff and the developer resolve where a recently installed water main should run.
District staff told the board that construction punch lists for the Rollins and Tuscher projects are nearly complete, but board members and a property owner urged holding final payment until a water-line alignment dispute is resolved.
Brandon (operations staff) said Rollins is finished pending administrative paperwork and a walk-through scheduled for the 28th to confirm punch-list completion. The Tuscher project is on punch-list items and the district has a…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat