The Metropolitan and Economic Development Committee voted to approve a payment-in-lieu-of-taxes pilot for Canal Village 3 LP, a proposed affordable-housing development financed in part with low-income housing tax credits under a program described in the meeting as "IC 30 six-three-two-twelve."
Get email alerts on the Canal Village 3 Pilot topic
No spam. Unsubscribe anytime.
The Metropolitan and Economic Development Committee voted to approve a payment-in-lieu-of-taxes pilot for Canal Village 3 LP, a proposed affordable-housing development financed in part with low-income housing tax credits under a program described in the meeting as "IC 30 six-three-two-twelve." The committee approved proposal 184 by voice vote after a developer update and a public-comment period featuring residents who said maintenance and tree-loss issues remain from Canal Village phase 1.
The project developer, Gary Hobbs, identified in the meeting as president and CEO of BWI, told the committee the developer completed many of the promised repairs and committed not to remove trees "unless it's absolutely necessary" for construction; he also said remaining fence work at Canal Village 1 will be finished by September. Hobbs asked the committee for support to approve the PILOT so construction on Canal Village 3 can begin next month.
The nut graf: the committee approved a tax-incentive pilot intended to support affordable units in Canal Village 3, but residents and neighborhood groups used the hearing to press the developer and city staff for stricter enforcement and clearer guarantees that remaining repairs and canopy restoration promised after phase 1 will be completed.
Residents and local advocates described continuing problems at Canal Village 1. Carolyn Watts, who identified herself as co-chair of Near Northwest communities, said she supports proposal 184 but objected to plans by a small subset of stakeholders who had not represented the entire neighborhood. Laurie Purdue of the Community Canopy Alliance and Ray Schnapp detailed tree loss on lots proposed for phase 3, citing field surveys that the speakers said identified heritage trees and estimated ecological benefits lost when canopy was removed. Purdue said one heritage tree on city park land at Frank Young Park was damaged.
Neighborhood leaders including Latroy Carter and Alita Kemp said many tenants reported delayed repairs, leaking roofs and other conditions that they said had persisted for years. A neighborhood representative who said she had been approached by Canal Village 1 residents urged the committee to ensure repairs are completed for homes not directly visible from public streets, and to maintain programs to help renters move toward homeownership.
DMD (the Department of Metropolitan Development) staff told the committee the city will use project agreements and the land-transfer terms to require architectural review, 15 years of affordability at 60% area median income, periodic DMD inspections during construction and the affordability period, and a right of reversion for city-owned lots if the developer fails to meet performance deadlines. The DMD speaker said the city can revoke the pilot or assess penalties for noncompliance and that the department had already required monthly project updates to the community until obligations are fulfilled.
Committee discussion noted the neighborhood's concerns and sought details about enforcement. Councilor Michael Paul Hart (District 20) asked what the city’s plan was to ensure developer compliance; DMD staff pointed to contractual remedies, inspection rights and the right to take back properties. When asked how residents could follow up, DMD staff directed residents to the mayor’s action center or to contact DMD staffers directly.
On the vote: the committee approved proposal 184 by voice vote. The meeting record shows the motion carried after the ayes and nays, but did not list a named mover, second or a numeric tally in the transcript; the minutes record the outcome as approved.
Ending: The approval allows Canal Village 3 to proceed toward closing and construction, subject to the city’s project agreements and ongoing oversight. Neighbors and advocates said they will continue to monitor repairs and tree-replacement commitments as the project moves forward.