Council awards Cadwell Park infield rebid; baseball liaison presses for DuraEdge subcontractor
Summary
Council approved a low bid from LT Companies for the Cadwell Baseball Field rebid project and authorized an additional contingency transfer; local baseball stakeholders urged use of baseball-specialist DuraEdge as subcontractor to warranty the infield mix.
Get email alerts on the Parks Recreation topic
No spam. Unsubscribe anytime.
Mitchell City Council voted to award the Cadwell Baseball Field rebid (Project 2025-3023R) to LT Companies following a public discussion about materials and installer qualifications. The low base bid was reported at $323,699; staff recommended the award and requested an additional contingency draw of $25,000 to fully fund the project.
At the meeting Jim Johnson, Mitchell Baseball Association liaison, raised concerns about awarding the contract to a firm without a track record installing full baseball infields using DuraEdge — a specialized infield mix discussed at length. Johnson said DuraEdge’s owner told him the company could come to Mitchell and perform and warranty the DuraEdge installation; LT Companies indicated a willingness to subcontract and learn under DuraEdge’s crew. After the public comment and staff explanation, Council member McCardell moved to award the contract to LT Companies; the motion was seconded by Council member Smith and carried.
City staff explained the project budget had a shortfall (the bid exceeded the prior allocation by roughly $9,000) and requested $25,000 from contingency to cover the increase. Finance staff warned there is limited contingency remaining in the overall budget and cautioned further additions.
Council and the public emphasized timing: proponents said DuraEdge and the chosen contractor expect to complete in a short window in September to allow turf establishment before winter. Council approved the award and the requested contingency transfer. The council did not attach a contractual requirement forcing a particular subcontractor; staff said they would recommend use of DuraEdge as the likely subcontractor if LT chooses to engage them.