Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

CIP update: Holford, Naaman School Road and senior center among 2019 bond projects nearing milestones

5595879 · August 18, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public works updated council on the 2019 bond program: Holford Road Segment A nearing completion, Naaman School Road under construction with long lead times, several drainage and street packages slated for 2026–27, and the senior activity center groundbreaking scheduled for the coming Saturday.

City engineering and project staff briefed council on the status of major 2019 bond projects and upcoming work.

Michael Polowczyk and project staff said Holford Road Segment A is roughly 90 percent complete (landscaping and remaining punch list items) and Naaman School Road — a constrained corridor with bridge work across Spring Creek — is under construction with an estimated substantial completion in 2027 because of utility relocations and railroad permits. Staff acknowledged internal…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans